Podiums
Podium Deck Membrane
Full podium deck membrane with drainage cell, protection layer and landscaping interfaces coordinated ahead of overburden.
- Location
- Belrose, NSW
- Sector
- Commercial / Mixed Use
- System
- Liquid-applied trafficable deck membrane
- Manufacturer
- Tremco
- Status
- Completed
Project Challenge
The deck carried landscaping, paving and services above the membrane, with no future access once overburden was placed.
VVS Solution
Detailing was completed and signed off at every penetration, upstand and outlet before broadcast application. The deck was flood tested and photographed in sections, then protected immediately.
Scope
- Substrate preparation and falls correction
- Full deck membrane installation
- Planter and pit detailing
- Flood testing prior to overburden
Areas Treated
- Podium slab
- Planters
- Pits and outlets
- Perimeter upstands
Construction Methodology
- Substrate assessment and moisture testing
- Grinding, patching and priming
- Reinforced detailing at all junctions
- Two-coat membrane to specified DFT
- Flood test and inspection hold point
- Protection board and drainage cell
Quality Assurance
- Coverage records per coat
- Batch numbers retained
- Photographic hold points
Photography
Project gallery
Similar project to price?
Send drawings, specifications or photographs and we'll respond with a detailed scope.